Of the following, which is NOT a concern of Monitor and Control Project Work?

A Stakeholder risk tolerance
B Comparing actual project performance against the project management plan
C Providing information to support status reporting
D Monitoring implementation of approved changes as they occur

1 Answer

5 votes

Final answer:

Stakeholder risk tolerance is not a direct concern of Monitor and Control Project Work; this process is focused on tracking project performance, managing changes, and status reporting.

Step-by-step explanation:

In the context of project management, Monitor and Control Project Work is concerned with tracking, reviewing, and regulating the progress and performance of a project. It specifically involves:

  • Comparing actual project performance against the project management plan.
  • Providing information to support status reporting, which is essential for keeping stakeholders informed.
  • Monitoring implementation of approved changes as they occur to ensure that changes are aligned with the project objectives.

Option A, Stakeholder risk tolerance, is not a direct concern of Monitor and Control Project Work; it is actually a component of the project's risk management process. Stakeholder risk tolerance impacts how risks are managed within a project, but monitoring and controlling project work itself is more focused on tracking the project's performance, managing changes, and communicating with stakeholders about the current state of the project.