Final answer:
The correct answer is A Requested changes. Perform Integrated Change Control is a process in project management that involves reviewing change requests, determining the potential impacts of those change requests, and deciding whether to approve or reject them.
Step-by-step explanation:
The correct answer is A Requested changes. Perform Integrated Change Control is a process in project management that involves reviewing change requests, determining the potential impacts of those change requests, and deciding whether to approve or reject them. The outputs of Perform Integrated Change Control include requested changes, project documents updates, change log, and project management plan updates. However, the exception in this question is requested changes.