All of the following are NOT inputs to Monitor and Control Project Work EXCEPT:

A Approved change requests.
B Work performance information.
C Risk register.
D Project baselines.

User Ggordon
by
8.1k points

1 Answer

3 votes

Final answer:

The Monitor and Control Project Work process in Project Management involves inputs such as approved change requests, work performance information, risk register, and project baselines.Therefore, the correct answer is A - Approved change requests.

Step-by-step explanation:

The subject of this question is Project Management.

In the Monitor and Control Project Work process, there are several inputs that are used to monitor and control the progress of a project. The inputs include:

  • Approved change requests: These are changes that have been requested and approved during the project. They may impact the project's scope, schedule, or budget. Monitoring and controlling these changes is important to ensure they are properly implemented.
  • Work performance information: This includes data and reports about the project's actual performance. It provides information on how well the project is progressing and whether it is meeting its objectives.
  • Risk register: This is a document that identifies and analyzes potential risks to the project. Monitoring and controlling the risk register helps to identify new risks, assess their impact, and implement risk response plans.
  • Project baselines: These are the original plans for the project, including the scope, schedule, and budget. Monitoring and controlling the project baselines involves comparing the actual progress of the project to the planned progress, identifying any variances, and taking corrective actions.