Final answer:
Implemented corrective actions is the output of the Direct and Manage Project Work process that realigns the performance of the project work with the project management plan.
Step-by-step explanation:
The correct answer is B) Implemented corrective actions.
In the Direct and Manage Project Work process, the project work is executed according to the project management plan. However, sometimes adjustments are needed to bring the project back on track. When there is a deviation from the plan, and an intentional activity is carried out to realign the performance of the project work with the project management plan, it is referred to as an implemented corrective action.