When is the 1st quarter optar grant posted to the Requisition/Optar log?

A) April 1st
B) January 1st
C) March 31st
D) December 31st

User Vmpn
by
7.3k points

1 Answer

3 votes

Final answer:

The 1st quarter optar grant is posted to the Requisition/Optar log on March 31st.

Step-by-step explanation:

The 1st quarter optar grant is posted to the Requisition/Optar log at March 31st.

User Dattel Klauber