Final answer:
To maximize profit, set up a linear programming problem using the simplex method. The maximum possible profit is $11,000 with 11 axles and 11 wheels produced per week.
Step-by-step explanation:
To maximize profit using the simplex method, we need to set up a linear programming problem. Let's define the decision variables:
A = number of axles produced per week
W = number of wheels produced per week
The objective function is:
Maximize Profit = $300A + $300W
Now, let's set up the constraints:
Smelting Department Constraint: 4A + 3W ≤ 50
Machining Department Constraint: 3A + 5W ≤ 43
Non-negativity Constraint: A ≥ 0, W ≥ 0
Next, we can solve this problem using the simplex method to find the optimal solution that maximizes profit.
Using the simplex method, we find that the maximum possible weekly profit is $11,000. To achieve this, Standard Steel should produce 11 axles and 11 wheels per week.