Which of the following is not a suggestion for controlling procurements?

a. Do not spend too much time documenting changes in writing; verbal agreements are fine
b. Have backup plans in case the procurement does not produce the desired results
c. Evaluation of any change should not include an impact analysis
d. Do not assume that work will run smoothly because you hired a reputable supplier

User Cherilyn
by
7.6k points

1 Answer

3 votes

Final answer:

Evaluation of any change should not include an impact analysis.

Step-by-step explanation:

The correct answer is c. Evaluation of any change should not include an impact analysis. When controlling procurements, it is important to evaluate any changes and assess their impact to ensure that they align with the desired results. This includes performing an impact analysis to understand the potential consequences of the change. By excluding impact analysis, there is a risk of making uninformed decisions that may negatively affect the procurement process.