Which of the following statements is false?

a. Even though many projects are canceled before completion, it is still important to formally close any project
b. Closing includes verifying that all of the deliverables are complete
c. Closing often includes a final presentation and report
d. Closing does not include developing a transition plan

User Keriann
by
7.9k points

1 Answer

2 votes

Final answer:

The false statement is that closing does not include developing a transition plan

Step-by-step explanation:

The false statement in this case is d. Closing does not include developing a transition plan. When closing a project, it is important to develop a transition plan to ensure a smooth handover of responsibilities and deliverables to the appropriate parties. This plan outlines the necessary steps and actions to be taken during the closing phase. It helps in ensuring that any project dependencies are addressed and the necessary support and documentation are provided to facilitate the transition.