Submittals are never critical, therefore they should not be included on the project time schedule

A-False
B-True

User Todd Price
by
6.9k points

1 Answer

6 votes

Final answer:

The assertion that submittals should not be included in the project time schedule is false. Submittals are vital for project progress, and their approval is essential for maintaining the project schedule.

Step-by-step explanation:

The statement that submittals are never critical and therefore should not be included on the project time schedule is false. Submittals are documents, samples, or other data that contractors send to the project's design team for approval before they proceed with the work or purchase the item. This could include drawings, schedules, material data, and other technical specifications that need to be checked to ensure they comply with the design intent.

Integrating submittals into the project time schedule is critical because their timely approval is essential for the progress of the project. Delays in the approval of submittals can lead to project delays, as contractors may need to wait for these approvals before proceeding with procurement or installation. Therefore, the management of submittals is a key aspect of project management, and they must be tracked and scheduled appropriately.

User Britany
by
7.5k points