109k views
5 votes
P,Q and R can do a piece of work in 18 days, 36 days and 54 day respectively. They start the work together but Q and R leave 1 day and 5 days respectively, before the completion of work. In how many days has the work been completed ?

User Adowrath
by
7.4k points

1 Answer

3 votes

The work has been completed in 108/11 days, which is approximately 9.82 days.

To determine the number of days it takes to complete the work, we can calculate the combined efficiency of P, Q, and R when they work together.

First, let's find the individual efficiencies of P, Q, and R by dividing the total work by the number of days each person takes to complete the work.

- P completes the work in 18 days, so their efficiency is 1/18 of the total work per day.

- Q completes the work in 36 days, so their efficiency is 1/36 of the total work per day.

- R completes the work in 54 days, so their efficiency is 1/54 of the total work per day.

Now, let's calculate the combined efficiency of P, Q, and R when they work together. We can add their individual efficiencies to get the combined efficiency.

Combined efficiency = 1/18 + 1/36 + 1/54

To add these fractions, we need to find the least common multiple (LCM) of the denominators, which is 108.

So, the combined efficiency is (6/108) + (3/108) + (2/108) = 11/108.

Now, let's find the total work that needs to be done. Since P takes 18 days to complete the work, the total work can be calculated as 18 times P's efficiency:

Total work = 18 * (1/18) = 1

Now, let's calculate the work done by P, Q, and R in the given number of days.

When Q and R leave the work:

- P completes 1/18 of the work in 1 day.

- Q completes 1/36 of the work in 1 day.

- R completes 1/54 of the work in 1 day.

So, in 1 day, the total work completed is (1/18) + (1/36) + (1/54) = 11/108.

To find the number of days it takes to complete the work, we can divide the total work (1) by the work completed in 1 day (11/108).

Number of days to complete the work = 1 / (11/108)

To divide by a fraction, we multiply by its reciprocal:

Number of days to complete the work = 1 * (108/11) = 108/11

Therefore, the work has been completed in 108/11 days, which is approximately 9.82 days

User Yoerids
by
8.1k points

No related questions found

Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.

9.4m questions

12.2m answers

Categories