109k views
5 votes
P,Q and R can do a piece of work in 18 days, 36 days and 54 day respectively. They start the work together but Q and R leave 1 day and 5 days respectively, before the completion of work. In how many days has the work been completed ?

User Adowrath
by
7.4k points

1 Answer

3 votes

The work has been completed in 108/11 days, which is approximately 9.82 days.

To determine the number of days it takes to complete the work, we can calculate the combined efficiency of P, Q, and R when they work together.

First, let's find the individual efficiencies of P, Q, and R by dividing the total work by the number of days each person takes to complete the work.

- P completes the work in 18 days, so their efficiency is 1/18 of the total work per day.

- Q completes the work in 36 days, so their efficiency is 1/36 of the total work per day.

- R completes the work in 54 days, so their efficiency is 1/54 of the total work per day.

Now, let's calculate the combined efficiency of P, Q, and R when they work together. We can add their individual efficiencies to get the combined efficiency.

Combined efficiency = 1/18 + 1/36 + 1/54

To add these fractions, we need to find the least common multiple (LCM) of the denominators, which is 108.

So, the combined efficiency is (6/108) + (3/108) + (2/108) = 11/108.

Now, let's find the total work that needs to be done. Since P takes 18 days to complete the work, the total work can be calculated as 18 times P's efficiency:

Total work = 18 * (1/18) = 1

Now, let's calculate the work done by P, Q, and R in the given number of days.

When Q and R leave the work:

- P completes 1/18 of the work in 1 day.

- Q completes 1/36 of the work in 1 day.

- R completes 1/54 of the work in 1 day.

So, in 1 day, the total work completed is (1/18) + (1/36) + (1/54) = 11/108.

To find the number of days it takes to complete the work, we can divide the total work (1) by the work completed in 1 day (11/108).

Number of days to complete the work = 1 / (11/108)

To divide by a fraction, we multiply by its reciprocal:

Number of days to complete the work = 1 * (108/11) = 108/11

Therefore, the work has been completed in 108/11 days, which is approximately 9.82 days

User Yoerids
by
8.1k points

No related questions found