If a job is finished 4 days early, what is its tardiness?

1 Answer

3 votes

Final answer:

The tardiness is 0 days since the job was completed ahead of schedule.

Step-by-step explanation:

To find the tardiness, you need to consider the difference between the planned duration of the job and the actual duration. If the job was finished 4 days early, it means that the actual duration was shorter than the planned duration. In this case, the tardiness is 0 days since the job was completed ahead of schedule.