What is the correct order of change control procedures regarding changes to systems and networks?

a) Request, Review, Approval, Implementation, Closure
b) Review, Request, Approval, Implementation, Closure
c) Request, Approval, Review, Implementation, Closure
d) Approval, Request, Review, Implementation, Closure

1 Answer

4 votes

Final answer:

The correct order of change control procedures for network and system changes starts with a Request, followed by Review, Approval, Implementation, and finally Closure.

Step-by-step explanation:

The correct order of change control procedures for changes to systems and networks is a sequence that ensures changes are organized, vetted, and processed in a way that maintains system integrity and reduces unforeseen complications. The right sequence is:

  1. Request: The change process begins with a request. This is when someone identifies the need for a change and formally requests it.
  2. Review: Next, the proposed change is reviewed. This step assesses the impact, feasibility, and other considerations of the change.
  3. Approval: After reviewing, the change must be approved by the appropriate stakeholders or change advisory board.
  4. Implementation: Once approved, the change can be scheduled and implemented according to the plan.
  5. Closure: Finally, after the change has been successfully implemented, the change is documented and closed.

Therefore, the correct answer is a) Request, Review, Approval, Implementation, Closure.