Final answer:
The WBS is the result of the Create WBS process, essential for breaking project deliverables into smaller parts for better project management.
Step-by-step explanation:
The Work Breakdown Structure (WBS) is the output of the Create WBS process. This process involves subdividing the major project deliverables into smaller, more manageable components. The Create WBS process is a critical step in the project management lifecycle and is part of the planning phase. A well-defined WBS helps in accurate project planning, scheduling, and monitoring, which are crucial for successful project delivery.