What is NOT included in the project charter?

1) The purpose of the project
2) high-level product requirements
3) Budget summary
4) Project Schedule

User Feofilakt
by
7.8k points

1 Answer

1 vote

Final answer:

The Project Schedule is not typically included in a project charter. Instead, the charter focuses on high-level aspects such as the purpose, initial requirements, and stakeholders.

Step-by-step explanation:

A project charter is a document that formally authorizes a project and provides a high-level roadmap for its execution, including initial requirements, stakeholders, and the overall scope.

However, it does not typically include detailed planning elements such as the Project Schedule.

The components explicitly mentioned to be not included in a project charter are: 1) the budget for product development, 2) the drawings used to design a product, 3) the engineering design process, and 4) the rate of the flow of water through a hose. These elements are generally developed in greater detail during the subsequent planning phase of the project.