The primary difference between a work breakdown structure and a work sequence draft is that the work sequence draft shows ________.

1) the additionally deployment tasks
2) the estimated effort of tasks
3) the day to day assignments
4) the sequence of tasks

1 Answer

2 votes

Final answer:

The work sequence draft shows the sequence of tasks, differentiating it from a work breakdown structure, which breaks down a project into smaller parts without detailing the order of tasks.

Step-by-step explanation:

The primary difference between a work breakdown structure (WBS) and a work sequence draft is that the work sequence draft shows the sequence of tasks. The WBS is a tool used in project management to break down a project into smaller, more manageable components, or work packages. On the other hand, a work sequence draft, often known as a project schedule or plan, lays out the order in which the tasks and activities will be carried out.

This order takes into consideration dependencies between tasks, resources allocation, and the timeline. The WBS does not inherently define the sequence or chronology of tasks. Instead, it provides a framework for what the project will deliver.