Products X and Y are assigned $100.00 in indirect costs by a traditional costing system. An activity analysis revealed that although production requirements are identical, X requires 45 minutes less setup time than Y. According to an ABC system, Y is _________ under the traditional system.

1) Undercosted
2) Overcosted
3) Fairly costed
4) Accurately costed

1 Answer

4 votes

Final answer:

According to the activity-based costing (ABC) system, if Product Y requires 45 minutes less setup time than Product X but both are assigned the same $100.00 in indirect costs under the traditional costing system, then Product Y is overcosted. Hence, the correct answer is option (2).

Step-by-step explanation:

According to the information given, the traditional costing system assigns $100.00 in indirect costs to both products X and Y. However, an activity analysis revealed that X requires 45 minutes less setup time than Y, indicating that Y is overcosted under the traditional system.

In an ABC system, costs are allocated based on activities, and in this case, the setup time is a relevant activity that affects the cost. Since Product Y requires less setup time but is assigned the same indirect costs as Product X under the traditional system, it suggests that Product Y is overcosted in the traditional costing system.

User Nitin Karale
by
8.6k points

No related questions found

Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.

9.4m questions

12.2m answers

Categories