Answer:
See below
Step-by-step explanation:
Given the above information
Payroll = $432,000 ÷ 4,800 = $90 per hour
Setup = $120,000 / 120 = $1,000 per setup
Material handling barrel = $104,400 / 8,700 = $11.95 per barrel
Quality control inspection = $264,000 / 1,100 = $240 per inspection
Overhead = $144,000 / 12,000 = $12 per machine hour
Details of the current product requirement
8 setup = 8 × $1,000 = $8,000
606 barrels = 606 × $11.95 = $7,242
80 inspections = 80 × $240 = $19,200
830 machine hours = 830 × $12 = $9,960
336 labor hours = 336 × $90 = $30,240
Total overhead assigned to order = $74,642