Gantt charts are more useful for scheduling, monitoring, and controlling the actual work than PERT charts.

1) True
2) False

User Jan Buchar
by
8.1k points

1 Answer

3 votes

Final Answer:

False. Gantt charts and PERT charts serve different purposes, with Gantt charts being more useful for visualizing schedules, and PERT charts excelling in complex project management and analysis. Option 2 is the answer.

Step-by-step explanation:

Gantt Charts: Gantt charts provide a visual representation of a project schedule, illustrating tasks and their timelines over time. While useful for scheduling and monitoring, Gantt charts may lack the depth and complexity required for certain projects, especially those with intricate dependencies.

PERT Charts: Program Evaluation and Review Technique (PERT) charts, on the other hand, are designed for complex projects. They emphasize the relationships and dependencies between tasks, incorporating probabilistic time estimates. PERT charts are valuable for analyzing critical paths, identifying potential bottlenecks, and managing uncertainty in project timelines.

Therefore, the statement is false as both charts have their distinct strengths and applications.

Option 2 is the answer.