88.5k views
4 votes
The three legs of the project triangle are management, staff, and clients.

1) True
2) False

User Htxryan
by
6.8k points

1 Answer

5 votes

Final answer:

The three legs of the project triangle are management, staff, and clients. This statement is false.

Step-by-step explanation:

The three legs of the project triangle are management, staff, and clients. This statement is false.

The project triangle, also known as the iron triangle or triple constraint, represents the three key components of a project: time, cost, and scope. It is used to illustrate the delicate balance between these elements and how changes in one will affect the other two.

Management, staff, and clients are important stakeholders in a project, but they are not the three legs of the project triangle.

User MANISHDAN LANGA
by
7.4k points