Adding more people to a project actually might increase the time necessary to complete the project because of a principle called _____.

1) Bernoulli's law
2) Moody's law
3) Hooke's law
4) Brooks' law

1 Answer

4 votes

Final answer:

Brooks' law states that adding more manpower to a late software project only makes it later, due to increased communication complexity and the time needed for new members to become productive.

Step-by-step explanation:

The principle you're asking about is known as Brooks' law. It is an observation in software development and project management which states that 'adding manpower to a late software project makes it later'. This seems counterintuitive but the reasoning behind it includes the time required for new personnel to get up to speed with the project, the increased complexity of communication as the team size grows, and the fragmentation of tasks which could lead to reduced efficiency.

Bernoulli's law, Moody's law, and Hooke's law are not related to this concept. They pertain to different areas of science, specifically physics and engineering. Bernoulli's law, for instance, relates to fluid dynamics and is applied to explain the behavior of liquids and gases under varying conditions.

User Demitrius Nelon
by
8.3k points