A _____ is a sequence of tasks that has no slack time.

1) baseline path
2) critical path
3) foundation path
4) risk path

1 Answer

7 votes

Final answer:

A critical path is a sequence of dependent tasks with no slack time, representing the longest stretch that determines the minimum time required for project completion. This is different from a system that follows the same path every cycle, as the critical path indicates where delays cannot occur without impacting the entire project duration.

Step-by-step explanation:

A critical path is a sequence of tasks that has no slack time. This indicates that it is the longest stretch of dependent activities (tasks), and any delay in this path will delay the project completion date. The critical path is crucial in project management as it represents the sequence of tasks that dictates the minimum amount of time required to complete a project. Unlike a baseline, foundation, or risk path, the critical path shows how each task is interconnected and which tasks cannot be delayed without affecting the project timeline.

When a system follows the same path for every cycle, it is following a predictable and defined process. However, that concept is different from the critical path in project management. The critical path is specific in that it identifies the longest duration of tasks without any excess time allotted.

Therefore, the correct answer to the student's question is option 2) critical path.