Produce network paths with a zero or positive total float?

User Tonyukuk
by
7.8k points

1 Answer

5 votes

Final answer:

To produce network paths with zero or positive total float, project managers perform forward and backward pass analyses to calculate total float for each activity, identifying the critical path with zero float and other paths with scheduling flexibility.

Step-by-step explanation:

To produce network paths with a zero or positive total float, we need to understand the concept of network paths in project management. A network path is a sequence of activities that leads from the start to the end of a project. The total float, also known as slack, is the amount of time that a task in a project network can be delayed without causing a delay to the project completion date.

Every network path has its own total float, and to identify the paths with zero or positive float, you must perform a forward pass and a backward pass analysis through the network. During the forward pass, you calculate the earliest possible start and finish times for each activity. Conversely, in the backward pass, you determine the latest start and finish times without delaying the project.

The difference between the latest and earliest finish times of each activity is the activity's total float. The critical path is the longest path through the network with the least total float, typically a float of zero. Any network path with a total float greater than zero indicates that there is additional time available for the activities on that path. Working with zero or positive total float ensures efficient schedule management and helps project managers to identify which activities have scheduling flexibility and which must be completed on time.