What are the Precedence Diagramming Method (PDM) Relationship Types?

1) Finish-to-Start (FS)
2) Finish-to-Finish (FF)
3) Start-to-Start (SS)
4) Start-to-Finish (SF)

User Prossblad
by
7.6k points

1 Answer

4 votes

Final answer:

The Precedence Diagramming Method (PDM) uses four relationship types: Finish-to-Start, Finish-to-Finish, Start-to-Start, and Start-to-Finish.

Step-by-step explanation:

The Precedence Diagramming Method (PDM) is a tool used in project management to show relationships between different activities in a project. The PDM represents these relationships using four types of relationship types:

  1. Finish-to-Start (FS): This is the most common and basic type of relationship. Activity A must finish before Activity B can start.
  2. Finish-to-Finish (FF): Activity A must finish before Activity B can finish.
  3. Start-to-Start (SS): Activity A must start before Activity B can start.
  4. Start-to-Finish (SF): Activity A must start before Activity B can finish.

These relationship types are important for understanding the sequence and dependencies between activities in a project.