Which of the following answers the questions of what, when, how much, and at times, where?

1) Project objective
2) Milestones
3) Technical requirements
4) Limits and exclusions

1 Answer

0 votes

Final answer:

Milestones answer the questions of what, when, how much, and at times, where.

Step-by-step explanation:

The answer that addresses the questions of what, when, how much, and at times, where is milestones. Milestones are specific goals or achievements that need to be reached within a project. They provide a clear timeline and measure progress towards the project objective. For example, if the project objective is to develop a new product, some milestones could be completing the design phase, finishing prototyping, and launching the product.