Final answer:
In PERT, tasks are analyzed and sequenced, the time for each task is estimated, and unknown quantities are identified for problem-solving. A bar graph is not typically associated with PERT, which uses network diagrams instead. Identifying supplies is not a primary focus in PERT.
Step-by-step explanation:
The Project Evaluation and Review Technique (PERT) includes specific steps that facilitate project management. Among these steps, the following are used in PERT:
-
Option D, creating a bar graph, is not typically associated with PERT. Instead, PERT charts usually involve network diagrams to visualize task sequences and duration.
While identifying supplies needed is relevant to project planning, it is not a primary focus of PERT, which is mainly concerned with scheduling and project timeline management.