What Knowledge Areas are found within the Closing Process Group?

User Caterham
by
9.4k points

1 Answer

5 votes

Final answer:

Within the Closing Process Group of the PMBOK, there are activities that involve several Knowledge Areas but not one dedicated solely to closing. Key processes include Closing Project or Phase and Close Procurements, entailing finalization of project activities and procurement arrangements.

Step-by-step explanation:

The question pertains to the Project Management Body of Knowledge (PMBOK) and specifically to the process groups and knowledge areas associated with project management. Within the Closing Process Group, there are several key activities that relate to finalizing all project activities. However, there is not a specific Knowledge Area dedicated solely to closing. Instead, the Closing Process Group utilizes processes from several Knowledge Areas to conclude project activities. The two primary processes within the Closing Process Group are:

  • Closing Project or Phase (Integration Management)
  • Close Procurements (Procurement Management)

These processes ensure that the project or a project phase is completed and closed appropriately, and that all contracts and procurement activities are finalized. The Closing Process Group works across all relevant knowledge areas to ensure that project deliverables are accepted, resources are released, and that all aspects of the project are brought to an orderly end.