Final answer:
The standard variable overhead rate for Sussex Company for May is calculated by dividing the budgeted variable overhead ($48,000) by the anticipated machine hours (24,000), resulting in a rate of Option A. $2.00 per machine hour.
Step-by-step explanation:
The student has asked to calculate the standard variable overhead rate for May for Sussex Company. The standard variable overhead rate is found by dividing the budgeted variable overhead by the anticipated machine hours of activity. Using the given data, the budgeted variable overhead is $48,000 and the anticipated machine hours are 24,000. Thus, the standard variable overhead rate is calculated as follows:
Standard Variable Overhead Rate = Budgeted Variable Overhead / Anticipated Machine Hours
Standard Variable Overhead Rate = $48,000 / 24,000 machine hours
Standard Variable Overhead Rate = $2.00 per machine hour.
Hence, the correct answer is A. $2.00.