47.5k views
2 votes
Abbott has a standard variable overhead rate of $4.50 per machine hour, and each unit produced has a standard time allowed of three hours. The company's static budget was based on 46,000 units. Actual results for the year follow.

Actual units produced: 42,000
Actual machine hours worked: 120,000
Actual variable overhead incurred: $520,000
Abbott's variable-overhead spending variance is:
A. $20,000 favorable.
B. $20,000 unfavorable.
C. $27,000 favorable.
D. $27,000 unfavorable.
E. not listed above.

User Techjacker
by
8.1k points

1 Answer

5 votes

Final answer:

Abbott's variable-overhead spending variance is $47,000 favorable, which means the actual overhead costs were less than expected for the actual level of activity. The provided options do not include the correct variance amount.

Step-by-step explanation:

The variable-overhead spending variance is the difference between the actual cost incurred for variable overhead and the expected cost at the actual level of activity.

Abbott's standard variable overhead rate is $4.50 per machine hour, and the standard time allowed per unit is three hours. With actual production at 42,000 units, the standard machine hours are 42,000 units × 3 hours/unit = 126,000 machine hours.

The expected variable overhead cost at the actual level of activity would be 126,000 hours × $4.50/hour = $567,000. However, the actual variable overhead incurred is $520,000.

Therefore, the variable-overhead spending variance is $567,000 (expected) - $520,000 (actual) = $47,000 favorable, which is not listed among the options provided.

User James Reed
by
8.9k points
Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.

9.4m questions

12.2m answers

Categories