Final answer:
The company should fill orders for Product CC first, then Product BB, followed by Product AA, as this sequence maximizes profits by prioritizing products with the highest contribution margin per machine hour.
Step-by-step explanation:
If demand exceeds the available capacity, the sequence in which orders should be filled to maximize the company's profits is by producing the product with the highest contribution margin per machine hour first.
To determine this, we calculate the contribution margin per machine hour for each product which is the contribution margin per unit divided by the machine hours per unit.
For Product AA, it's £10 / 2 hours = £5 per machine hour. For Product BB, it's £13 / 1.5 hours = £8.67 per machine hour. For Product CC, it's £5 / 0.5 hours = £10 per machine hour. Therefore, the company should fill orders for Product CC first, Product BB second, and Product AA last.
Answer: c. Product CC first, Product BB second, and Product AA third