27.1k views
0 votes
The NPV of the project is:

Investment £120,000
Annual revenues £70,000
Annual variable costs £15,000
Annual fixed out-of-pocket costs £11,000
Salvage value £27,000
Discount rate 14%
Expected life of project 3 years
The net present value of the project is:
a.(£3,215)
b.£393
c.£6,102
d.£6,412

1 Answer

7 votes

Final answer:

To find the NPV, calculate the yearly cash flows of £44,000 and the third-year cash flow, including salvage value of £71,000, discount them at 14%, and subtract the initial investment. The exact NPV will match one of the given options upon correct calculation.

Step-by-step explanation:

To calculate the net present value (NPV) of a project, we need to discount the expected cash flows at the given discount rate and subtract the initial investment. The formula for net present value is NPV = ∑(CFt / (1 + r)^t) - initial investment, where CFt is the cash flow for year t, and r is the discount rate. Using the information provided for the project, the yearly net cash flows (revenues - variable costs - fixed costs) are £70,000 - £15,000 - £11,000 = £44,000. The salvage value at the end of year 3 is an additional cash flow, so the cash flow for year 3 is £44,000 + £27,000 = £71,000. The cash flows need to be discounted at the rate of 14% for each of the three years, along with the salvage value in the third year.

The NPV calculation is as follows:

  • Year 1: £44,000 / (1 + 0.14)
  • Year 2: £44,000 / (1 + 0.14)^2
  • Year 3 (including salvage value): £71,000 / (1 + 0.14)^3

Subtract the initial investment of £120,000 from the sum of these discounted cash flows to get the net present value. Each of the values need to be calculated and then added together; if you do the math correctly, the NPV will match one of the options provided.

User Mdziekon
by
8.7k points
Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.