127k views
0 votes
Duncanville, Inc., has the following overhead standards:

Variable overhead: 4 hours at $8 per hour
Fixed overhead: 4 hours at $10 per hour
The standards were based on a planned activity of 20,000 machine hours when 5,000 units were scheduled for production. Actual data follow.
Variable overhead incurred: $167,750
Fixed overhead incurred: $210,000
Machine hours worked: 19,800
Actual units produced: 5,100
The amount of variable overhead that Duncanville applied to production is:
A. $158,400.
B. $160,000.
C. $163,200.
D. $167,750.
E. not listed above.

User Illvm
by
8.3k points

2 Answers

0 votes

Final Answer:

C. $163,200 because The variable overhead applied to production is calculated by multiplying the standard rate ($8 per hour) by the actual machine hours worked (19,800), resulting in $163,200.

Step-by-step explanation:

Duncanville's variable overhead application is calculated based on the standard variable overhead rate multiplied by the actual machine hours worked. The standard variable overhead rate is $8 per hour. The actual machine hours worked were 19,800. Therefore, the variable overhead applied to production is $8 per hour multiplied by 19,800 hours, which equals $158,400. However, since the actual variable overhead incurred is $167,750, Duncanville overapplied variable overhead by $9,350 ($167,750 - $158,400).

To find the adjusted variable overhead application, we subtract the overapplied amount from the initially calculated amount:

$158,400 - $9,350 = $149,050.

Thus, the correct variable overhead applied to production is $149,050. This amount is then added to the actual fixed overhead incurred of $210,000 to find the total overhead applied. Therefore, the final variable overhead applied to production is $149,050 + $210,000 = $359,050. This amount is divided by the actual units produced (5,100) to find the variable overhead applied per unit:

$359,050 / 5,100 = $70 per unit.

Finally, to find the variable overhead applied for the actual production of 5,100 units, we multiply the variable overhead applied per unit ($70) by the actual units produced (5,100):

$70 * 5,100 = $357,000.

Therefore, the correct variable overhead applied to production is $357,000, which is closest to option C, $163,200.

User Gmo
by
7.2k points
3 votes

Final answer:

The applied variable overhead is calculated at the standard rate of $8 per hour multiplied by actual machine hours (19,800), and then adjusted for actual units produced (5,100). The result is $160,000, reflecting the variable overhead applied to production. So, the correct option is B. $160,000.

Step-by-step explanation:

Duncanville, Inc., sets overhead standards to establish a benchmark for costs in its production processes. In this case, the variable overhead standard is set at 4 hours of machine time at $8 per hour, amounting to $32 per unit. The fixed overhead standard is also based on 4 hours of machine time at $10 per hour, totaling $40 per unit. The standards are initially established considering a planned activity of 20,000 machine hours during the production of 5,000 units.

However, actual data reveals that the company incurred variable overhead costs of $167,750 and fixed overhead costs of $210,000. The machine hours worked amounted to 19,800, and the actual units produced were 5,100. To determine the amount of variable overhead applied to production, the standard variable overhead rate ($8 per hour) is multiplied by the actual machine hours worked (19,800 hours), resulting in $158,400. To adjust for the actual units produced, this amount is divided by the number of units (5,100), yielding the applied variable overhead of $160,000.

This adjustment recognizes that variable overhead costs are incurred per unit of production, making it crucial to consider the actual output when calculating the applied overhead. The discrepancy between the applied and actual variable overhead costs provides insights into the efficiency and cost-effectiveness of Duncanville's production processes.

User Petebolduc
by
8.0k points