In the R.S. Means system, what is/are the bare cost(s) that is/are specified for each line item? A) the direct cost of equipment B) the direct cost of materials C) the direct cost of labor D) the contractor's profit

1 Answer

4 votes

Final answer:

In the R.S. Means system, the bare costs for each line item typically include the direct cost of materials, labor, and equipment, but not the contractor's profit.

Step-by-step explanation:

In the R.S. Means system, the bare costs specified for each line item typically include the following: B) the direct cost of materials, C) the direct cost of labor, and A) the direct cost of equipment. These costs are the essential expenses incurred for a construction project and are used to calculate the total project cost.

These costs do not inherently include D) the contractor's profit, which is a separate consideration when determining final project pricing. The R.S. Means system is designed to provide a detailed breakdown of construction costs to ensure that all factors are accounted for in a transparent and comprehensive manner.

User Eugen Konkov
by
8.2k points

No related questions found

Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.