In the R.S. Means system, what is/are the bare cost(s) that is/are specified for each line item? A) the direct cost of equipment B) the direct cost of materials C) the direct cost of labor D) the contractor's profit

1 Answer

4 votes

Final answer:

In the R.S. Means system, the bare costs for each line item typically include the direct cost of materials, labor, and equipment, but not the contractor's profit.

Step-by-step explanation:

In the R.S. Means system, the bare costs specified for each line item typically include the following: B) the direct cost of materials, C) the direct cost of labor, and A) the direct cost of equipment. These costs are the essential expenses incurred for a construction project and are used to calculate the total project cost.

These costs do not inherently include D) the contractor's profit, which is a separate consideration when determining final project pricing. The R.S. Means system is designed to provide a detailed breakdown of construction costs to ensure that all factors are accounted for in a transparent and comprehensive manner.

User Eugen Konkov
by
8.5k points