[T/F] When picking a bid through a negotiated contract, all design documentation must be complete at the time of negotiation

User PakitoV
by
7.2k points

1 Answer

0 votes

Final answer:

The requirement for complete design documentation at the time of negotiation is not strict and can vary. Negotiations for a bid can proceed with incomplete documentation, especially in complex projects or certain delivery methods like design-build or IPD.

Step-by-step explanation:

The statement 'When picking a bid through a negotiated contract, all design documentation must be complete at the time of negotiation' is not necessarily true. While having complete design documentation can be beneficial, it is not a strict requirement for the negotiation phase.

In some cases, negotiations can occur on the basis of incomplete design documentation, especially if the project involves complex engineering or architectural work where design development and construction can proceed concurrently. This can happen in cases where there’s a fast-track schedule or when the project delivery method allows for some level of flexibility, such as in design-build or integrated project delivery (IPD).

However, it's essential to acknowledge that the development of a detailed design is a critical step that has a significant impact on the success of the project. Poor design decisions made early in the process can lead to a product that fails to meet customer needs.