A forward pass through a network is used to determine the earliest start times and earliest finish times for each project activity.

True or False

1 Answer

2 votes

Final answer:

A forward pass is used to determine the earliest start and finish times for each activity in a project.

Step-by-step explanation:

A forward pass through a network is used to determine the earliest start times and earliest finish times for each project activity.

This statement is true.

A forward pass is a critical path method technique used to calculate the earliest start and finish times for all project activities. It helps in identifying the project's critical path, which is the sequence of activities that would cause a delay if any activity within it is delayed.

By determining the earliest start and finish times for each activity, project managers can better plan and schedule resources, and keep the project on track.