A(n) _____ determines the early start and early finish dates for each activity in a project.

A) Forward Pass
B) Backward Pass
C) Critical Path Method (CPM)
D) Resource Leveling

1 Answer

3 votes

Final answer:

The A) 'Forward Pass' determines the early start and early finish dates for each activity in a project by moving through the project schedule and calculating the earliest possible times for each activity to start and to finish.

Step-by-step explanation:

The correct answer to the question "A(n) _____ determines the early start and early finish dates for each activity in a project." is A) Forward Pass. A forward pass is a technique used in project management to determine the early start (ES) and early finish (EF) dates for each activity in a project schedule. The process involves moving through the project schedule from the beginning to the end, calculating the earliest time that each activity can start and finish, given that its preceding activities are finished. It is important to note that this is different from the Backward Pass, which is used to determine the latest start and latest finish times, and the Critical Path Method (CPM), which identifies the sequence of critical activities that determines the project duration. Resource Leveling is a technique used to address resource allocation; it is not directly used for determining early start and finish dates.

User Daniel Lyon
by
8.2k points