In project time management, which of the following processes generate the main outputs of an activity list, activity attributes, and a milestone list?

a) Defining activities
b) Developing the schedule
c) resource estimating activities
d) Estimating activity durations

1 Answer

4 votes

Final answer:

In project time management, the a) 'Defining activities' process produces the activity list, activity attributes, and milestone list, which break down work packages into manageable tasks and provide detailed information needed for planning.

Step-by-step explanation:

In project time management, the processes that generate the main outputs of an activity list, activity attributes, and a milestone list are part of 'Defining activities'. When defining activities, project teams break down work packages into smaller, more manageable components known as activities. This process ensures that all tasks necessary for the completion of the work packages are identified and described in detail.

The activity list includes all schedule activities required for project completion and serves as a basis for developing the schedule and performing other project management processes. Activity attributes provide information about each activity like resources required, locations, durations, and constraints, which are necessary for further project planning. A milestone list identifies all milestones and indicates whether they are mandatory, such as those required by contract, or optional based on the project team's decisions.