Critical chain scheduling protects tasks on the critical chain from being delayed by using _____, which consist of additional time added before tasks on the critical chain that are preceded by non-critical-path tasks.

A) Padding
B) Buffers
C) Reserves
D) Contingencies

1 Answer

7 votes

Final answer:

In critical chain scheduling, tasks on the critical chain are protected from delays by using buffers, which are additional time allowances placed before critical tasks that follow non-critical tasks. Option b.

Step-by-step explanation:

Critical chain scheduling protects tasks on the critical chain from being delayed by using buffers option b, which consist of additional time added before tasks on the critical chain that are preceded by non-critical-path tasks. These buffers are strategically placed to absorb the variability in task durations and to ensure that any delays in non-critical tasks do not affect the critical tasks, thereby protecting the project timeline. Using buffers increases the chances of completing projects on time by guarding against uncertainties.

User Janemarie
by
7.4k points