Final answer:
AOA network diagrams use only finish-to-start dependencies.exclusively utilize finish-to-start dependencies, representing tasks that must be finished before subsequent tasks can commence.
Step-by-step explanation:
AOA network diagrams use only finish-to-start dependencies.
Finish-to-start (FS) is a type of dependency where the predecessor activity must finish before the successor activity can start. In AOA network diagrams, the activities are represented by nodes, and the dependencies between them are represented by arrows. An FS dependency means that an activity cannot start until its preceding activity has finished.
For example, let's say you are planning a project to build a house. The tasks might include pouring the foundation, framing the walls, installing electrical wiring, and painting. The pouring of the foundation must be finished before the framing of the walls can start, so this is an FS dependency.