The project manager should be more skilled at __________, whereas the functional manager should be more skilled at __________.

a) Technical expertise, Leadership
b) Team building, Decision-making
c) Planning, Control
d) Negotiation, Conflict resolution

User Brian Yeh
by
8.2k points

1 Answer

5 votes

Final answer:

The project manager should be more skilled at planning and control, whereas the functional manager should be more skilled at team building and decision-making.

Step-by-step explanation:

The project manager should be more skilled at planning, control, whereas the functional manager should be more skilled at team building, decision-making.

Planning and control are important skills for a project manager as they involve outlining the objectives, creating a roadmap, and monitoring progress to ensure that the project is on track. On the other hand, team building and decision-making are crucial skills for a functional manager as they require the ability to create a cohesive team and make effective decisions for the department.