__________ refers to the modifications to the project plan. In many cases, the projects get larger.

A) Schedule change
B) Budget adjustment
C) Scope change
D) Resource reallocation

1 Answer

3 votes

Final answer:

Scope change refers to modifications to the project plan that may lead to adjustments in the project's schedule, budget, and resource allocation.

Step-by-step explanation:

The correct answer is C) Scope change.

Scope change refers to the modifications to the project plan. In many cases, the projects get larger. When the scope of a project is changed, it means that new tasks or activities are added, or existing ones are modified. This can result in adjustments to the project schedule, budget, and resource allocation.

For example, if a construction project originally planned to build a small house but then the client decides to add additional rooms and features, it would require a scope change. This would lead to changes in the project's schedule, budget, and allocation of resources to accommodate the expanded scope of work.