Toward the end of the project lifecycle, Thamhain et al say that conflict intensity is the greatest with respect to schedules. Which of the following options is correct?

a) Resource allocation
b) Budget constraints
c) Scope changes
d) Stakeholder communication

User Cream
by
8.7k points

1 Answer

7 votes

Final answer:

At the end of the project lifecycle, the greatest conflict intensity regarding schedules is associated with Resource allocation, as resources like personnel and equipment become more constrained.

Step-by-step explanation:

Toward the end of the project lifecycle, Thamhain et al. indicate that conflict intensity is the greatest with respect to schedules. The correct option that describes this type of conflict is Resource allocation (a). As projects approach their deadlines, scheduling conflicts typically escalate due to limited availability of resources needed to complete the remaining tasks. These resources may include personnel, equipment, or materials that are necessary for the final stages of the project. Effective resource management throughout the project lifecycle is critical to mitigating these challenges and ensuring that the project remains on track.

User Stefan Profanter
by
7.0k points