Final answer:
The true statement regarding relative priorities for project selection using non-numeric models is that priorities are determined by subjective judgments.
Step-by-step explanation:
In project selection using non-numeric models, the true statement regarding relative priorities is that priorities are determined by subjective judgments (option b). In this method, projects are evaluated based on non-financial criteria such as strategic alignment, risk level, and resource availability. Unlike numeric models that use financial metrics, non-numeric models take into account qualitative factors for decision-making.
For example, if a company wants to prioritize projects that align with its long-term strategic goals, it may give higher priority to a project that supports sustainability initiatives, even if it has lower financial returns.
Relative priorities in project selection using non-numeric models are not fixed and unchangeable (option d). They can vary based on changing circumstances or new project opportunities.