Final answer:
The total cost for Job 15 at Vermillion Company is calculated by summing the opening balance, direct materials, direct labor, and various overhead costs based on activity-based costing rates, resulting in a total cost of $104,600.
Step-by-step explanation:
To calculate the total cost for Job 15 at Vermillion Company using activity-based costing, we need to add up all the costs associated with the job. First, we begin with the opening balance and add the direct materials and direct labor costs:
- Opening balance: $32,000
- Direct materials: $26,000
- Direct labor: $30,000
Next, we need to calculate the overhead costs based on the activity-based costing rates provided:
- Engineering design overhead: 25 engineering hours × $40 per hour = $1,000
- Purchasing overhead: 120 parts × $10 per part = $1,200
- Other overhead: 1,800 direct labor hours × $8 per hour = $14,400
Adding these overhead costs to the initial aggregate:
Total cost = Opening Balance + Direct Materials + Direct Labor + Engineering Design Overhead + Purchasing Overhead + Other Overhead
Total cost = $32,000 + $26,000 + $30,000 + $1,000 + $1,200 + $14,400
Therefore, the total cost for Job 15 is:
$32,000 + $26,000 + $30,000 + $1,000 + $1,200 + $14,400 = $104,600