92.6k views
3 votes
Reedy Builders, Inc. is using the completed-contract method for a $12,500,000 contract that will take three years to complete. Data at December 31, 2015, the end of the first year, are as follows:

Costs incurred to date $6,240,000
Estimated costs to complete $6,660,000
Billings to date $5,920,000
Collections to date $5,540,000
The gross profit or loss that should be recognized for 2015 is:

a. $320,000 loss.
b. $0.
c. $400,000 loss.
d. $133,334 loss

User Razimbres
by
7.4k points

1 Answer

1 vote

Final answer:

Under the completed-contract method, Reedy Builders would recognize a gross profit or loss of $0 for the year 2015 because the contract is not completed, and revenue and profit recognition is deferred until completion.

Step-by-step explanation:

The gross profit or loss to be recognized by Reedy Builders, Inc. for 2015 under the completed-contract method would be $0 since this accounting method recognizes revenues and gross profit only when a contract is substantially complete. At the end of the first year, the contract in question is not yet completed, and therefore no gross profit or loss should be recognized.

User Gkkirsch
by
7.3k points