Final answer:
The IRR of the project is approximately 18.53%. Oriole should go ahead with this project as the cost of capital is lower than the IRR.
Step-by-step explanation:
To calculate the Internal Rate of Return (IRR) of a project, we need to determine the discount rate at which the present value of expected cash inflows equals the initial investment. In this case, the initial investment is $7,488,051 and the expected cash flows are $1,725,000 per year for six years. The IRR is the rate at which the Net Present Value (NPV) of the project is zero.
Using the formula NPV = -Initial Investment + (Cash Flow / (1 + Discount Rate) ^ Year), we can calculate:
0 = -7,488,051 + (1,725,000 / (1 + IRR) ^ 1) + (1,725,000 / (1 + IRR) ^ 2) + ... + (1,725,000 / (1 + IRR) ^ 6)
By trial and error, we find that the IRR of this project is approximately 18.53%.
Since the appropriate cost of capital is 12%, which is lower than the IRR of the project, Oriole should go ahead with this project. It is expected to generate a positive return and is therefore financially viable.