123k views
1 vote
Lilac Corporation manufacturers lilac products. All goods pass through two processes: Assembly and Finishing. They use a process costing system to track their manufacturing costs. Lilac Corporation began the period with 9,900 physical units valued at $179,200. Of that amount, $70,200 relates to direct material costs.

During the period they began production an additional 16,000 units. During the production process, they incurred additional direct materials cost of $62,300, 9,610 direct labor hours, and 12,500 machine hours.
At the end of the period, 17,400 physical units were transferred to the Finishing process. The remaining units were 80% complete with respect to direct materials, and 60% complete with respect to the conversion process. All laborers were paid at a wage rate of $10.00 per house, and overhead costs are allocated using a predetermined overhead rate of $6.56 per machine hour. Using the information provided, please calculate the following amounts.
A. Per unit cost to complete the Assembly process__________________
B. Ending Assembly work in process balance __________________
C. Costs transferred to the Finishing work in process account __________________

1 Answer

6 votes

Final answer:

To compute the Assembly process costs, one needs to add the beginning inventory, labor, overhead, and additional direct materials costs, then divide by the units transferred to find the per unit cost. The ending Assembly WIP balance and costs transferred out are based on the level of completion. The exact figures cannot be calculated with the information provided; only the methods have been outlined.

Step-by-step explanation:

To calculate per unit cost for the completed Assembly process (A), direct materials, labor, and overhead costs are combined and divided by the number of units transferred to the Finishing process. We first calculate total labor and overhead costs using the labor hours, wage rate, machine hours, and overhead rate provided. Then, we add beginning inventory and incurred direct material costs.

The ending Assembly work in process balance (B) is the costs attributed to the units that have not been fully processed. This is calculated by considering the degree of completion with respect to direct materials and conversion costs for the remaining units in the Assembly process.

The costs transferred to the Finishing work in process account (C) encompass all costs associated with the units that have been completed in the Assembly process and are now moving on to the Finishing process.

Please note that without the specific value for total labor and overhead costs as well as the beginning work in process inventory split between direct materials and conversion costs (not provided in the question), we cannot compute the exact dollar amount. This explanation provides the methodology to be applied once all necessary figures are available.

User Daniel Jonsson
by
7.4k points