Final answer:
The Net Present Value (NPV) of the project, based on the given information, is -$2,600.
Step-by-step explanation:
The Net Present Value (NPV) of a project is calculated by discounting the cashflows at the risk-free discount rate and then subtracting the initial cost of the project. To calculate the NPV, we first need to calculate the present value of each cashflow in the project's timeline. The present value is calculated by multiplying each cashflow by its corresponding certainty equivalent coefficient, and then discounting it at the risk-free discount rate of 10%. Finally, we sum up all the present values and subtract the initial cost of the project to get the NPV.
Let's calculate the present value for each cashflow:
- Year 1: $12,000 * 0.90 = $10,800
- Year 2: $14,000 * 0.70 = $9,800
- Year 3: $10,000 * 0.50 = $5,000
- Year 4: $6,000 * 0.30 = $1,800
Next, we calculate the NPV by summing up the present values and subtracting the initial cost of the project:
NPV = $10,800 + $9,800 + $5,000 + $1,800 - $30,000 = -$2,600
Therefore, the NPV of the project is -$2,600.