Final answer:
The total standard cost per unit is $408.30. The total actual cost per unit is $1,554.10.
Step-by-step explanation:
The total standard cost per unit can be calculated by adding up the standard costs of raw materials, direct labor, variable overhead, and fixed overhead. For raw materials, the standard usage is 2 feet per unit at a price of $8.45 per foot. So the standard cost for raw materials per unit is $16.90. For direct labor, the standard hours per unit is 1.4 hours at a rate of $16.00 per hour. So the standard cost for direct labor per unit is $22.40. For variable overhead, the standard application rate is $2.50 per direct labor hour, which means the standard cost per unit is $2.50 multiplied by the actual hours used, which is 43,500 hours, resulting in a total of $108,750. And for fixed overhead, the standard application rate is $6.00 per direct labor hour, which means the standard cost per unit is $6.00 multiplied by the actual hours used, which is 43,500 hours, resulting in a total of $261,000. Adding up all these standard costs gives us the total standard cost per unit of $408.30.
The total actual cost per unit can be calculated by adding up the actual costs of raw materials, direct labor, variable overhead, and fixed overhead. For raw materials, the actual usage is 64,000 feet, which is $8.55 per foot, resulting in a total of $547,200. For direct labor, the actual total direct labor cost is $687,300. For variable overhead, the actual variable overhead cost is $108,000. And for fixed overhead, the actual fixed overhead cost is $211,800. Adding up all these actual costs gives us the total actual cost per unit of $1,554.10.