Final answer:
The payback period is 10 years. The NPV is $380,885. Investing in the original project is recommended.
Step-by-step explanation:
To calculate the payback period, we divide the initial investment ($4 million) by the annual cash flow ($400,000). In this case, the payback period is 10 years. Therefore, the correct answer for part (a) is 10 years.
To calculate the NPV, we discount each cash flow to its present value and then subtract the initial investment. Using a discount rate of 9%, the NPV is approximately $380,885. Therefore, the correct answer for part (b) is $380,885.
If we wait three years to invest in the new project with improved technology, the new project will have a higher investment cost ($5 million) but also higher cash flows ($500,000). To determine whether to invest now or wait, we can calculate the NPV of the new project using the same discount rate. Comparing the NPV of the original project ($380,885) and the NPV of the new project, we can see that the original project has a higher NPV. Therefore, I would recommend investing in the original project rather than waiting.