18.2k views
4 votes
The Corporation is considering a project which requires an expenditure of $100,000 initially, at t = 0. It will then obtain additional revenues from sales of $150,000 per year for the next two years (t = 1 and t = 2) with expenses of $30,000 per year for operating costs attributed to the project but not including the depreciation of the initial expenditure of the $100,000. The depreciation used is straight-line with zero salvage, meaning an equal amount each year for the two-year life of the project. Masefield's weighted average cost of capital is 12.69% and it is taxed at a 30% rate. What is the net present value for the project?

1 Answer

3 votes

Final answer:

The net present value (NPV) of the project is $51,915.

Step-by-step explanation:

To calculate the net present value (NPV) of the project, we need to determine the present value of the cash flows associated with it. The initial expenditure of $100,000 is not considered in the NPV calculation as it is a sunk cost. The additional revenues of $150,000 per year for the next two years can be discounted using the weighted average cost of capital (WACC). The WACC for the corporation is 12.69% and it is taxed at a 30% rate.

To calculate the present value of the revenues, we use the formula: PV = CF / (1 + r)^n, where PV is the present value, CF is the cash flow, r is the discount rate, and n is the number of periods. In this case, the present values of the revenues for t = 1 and t = 2 are $132,703 and $118,212, respectively.

The net present value (NPV) is calculated by subtracting the initial expenditure from the present value of the revenues. Therefore, the NPV of the project is $51,915.

User Glyn
by
7.3k points

No related questions found

Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.

9.4m questions

12.2m answers

Categories